Ichthys LNG

Client

East Arm Civil

Locations

Bladin Point, Wickham, Northern Territory 0822, Australia

Tags

Ichthys LNG

We manufactured and installed:

  • 9700 lineal metres of TR20 handrail on the reservoir wall
  • 20000 lineal metres of 2400mm-high chainmesh fence with three rows of barbed wire on the perimeter

To beat the wet season, we needed to install the handrail at an average of 300m per day at times working at heights and in harsh conditions. This stage of the project was completed in record time with stringent safest measures.

The INPEX Icthys LNG Project comprises advanced offshore facilities linked to massive onshore facilities via an 889km pipeline.